Weekly Status Update — Template¶
Use this every Friday by EOD. Post in the client Slack channel AND as an Asana Update on the engagement project. The Asana version goes to the EM and Bill; the Slack version is for the broader engagement audience.
This is the Updates + 4 Blockers format from Asana tutorial video 11. Don't invent a different format — consistency is the value.
The format (copy/paste this)¶
Status: [On Track | At Risk | Off Track]
Period: Week of <Mon date> – <Fri date>
What got done this week:
- <Outcome, not activity. "Stood up X" not "worked on X">
- <…>
What's next week:
- <Specific deliverables with owners and dates>
- <…>
4 Blockers (or "None" if truly none):
1. <Blocker> — owner: <name> — needed by: <date>
2. <Blocker> — owner: <name> — needed by: <date>
3. <…>
4. <…>
Decisions needed from <EM / Bill / client>:
- <Question that needs an answer this week>
Rules¶
- BLUF. The status flag (On Track / At Risk / Off Track) is the first thing the reader sees. If it's At Risk or Off Track, the next line should say why in plain English.
- Outcomes, not activity. "Worked on the project plan" is not a status; "project plan v1 complete, EM review pending" is.
- A blocker has a name and a date. "Waiting on client" is not a blocker. "Waiting on Kathleen for the comp data dump, needed by Wed for the model" is.
- Length cap: one Slack message that doesn't require expansion. If it's longer, you're either reporting too granularly or you're using the status update as your task list. Don't.
What "Status: On Track" actually means¶
| Flag | Meaning |
|---|---|
| On Track | All committed deliverables this week landed. Next week's plan is realistic. |
| At Risk | One or more deliverables slipped or are likely to slip. You see a path back. |
| Off Track | Slippage that can't be recovered without scope, time, or resource adjustment. Requires an EM conversation, not just a status flag. |
Default to At Risk over On Track when it's ambiguous. We'd rather over-flag and self-correct than discover the slip at the Steerco.
Worked example¶
Status: At Risk
Period: Week of Mar 3 – Mar 7
What got done this week:
- Pipeline inspection v2 delivered to Bill; minor edits incoming
- Sander onboarded to Linden engagement; access provisioned
- Steerco #3 deck shell drafted; ready for EM content fill
What's next week:
- Pipeline inspection v3 with Bill's edits by Wed
- Steerco #3 dry run with EM by Thu; live Steerco Fri
- 1099 onboarding checklist v1 draft for onboarding mentor review
4 Blockers:
1. Need Kathleen's comp data dump — owner: Kathleen (client) — needed by: Tue 3/11
2. Steerco deck content for slides 7-12 — owner: EM — needed by: Thu 3/13
3. None
4. None
Decisions needed from EM:
- Are we keeping the optional slide on territory rebalancing in Steerco #3, or pushing to Steerco #4?
After you've sent it¶
- Confirm receipt with the EM (a thumbs-up reaction is enough)
- Open Asana and mark the matching tasks as complete or update their status
- Capture any new action items from the post-update conversation as Asana tasks before EOD Friday — don't let them spill into the weekend